Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

The Gallery | Tunnel boring machine cutter lifted to surface for repair

Specialist heavy lifting contractor Mammoet has released images of the 16-hour operation to lift a 1,700t tunnel boring machine cutter to the surface in Seattle.

After a year of planning, Seattle-based Mammoet has lifted out the Cutter Drive Unit (CDU) from tunnel boring machine ‘Bertha’. The unit was lifted to the surface, rotated to lie face down and then skidded onto supports ready to be repaired.

In December 2013 Bertha stalled 36.5m underground, while boring from South Main Street to the Alaskan Way Viaduct in Seattle.

The repairs could not be completed, so a deep, concrete-lined shaft was created down to the cutter.

The lifting of the heavy CDU was complex due to its shape and asymmetrical weight distribution. Weighing 1,700t and with a diameter of 17.5m, the cutter was located close to a highway with complex soil stability.

A special gantry mounted on a skid system was designed to lift the tunnel cutter. The gantry was supported on twin rows of concrete pillars, originally designed for stabilising the surrounding soil during tunnelling. Using the pillars as foundations the gantry was constructed across shaft.

Engineers developed the design in four weeks. Using steel beams a specialised modular tower was constructed to safely support the weight of the load.

The concrete foundations were not designed to support a load at height, so engineers devised a hydraulic equalisation system to place under the tower. Made up of 48 hydraulic cylinders, the system was designed to help the gantry withstand wind and tail forces when skidding.

Once the repairs are completed, the CDU will be manoeuvred back down the shaft and reinstalled in the machine ready to complete the Highway 99 tunnel.

 

 

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.