Wickford Primary School

Project 110

Key innovation: pain/gain share

The NEC option C target contract with activity schedule had the interesting addition of a contingency fund, established outside the target, to fund risks identified by all members of the team. Unused funds were split between all parties - including the consultant - on conclusion of the project.

The team

Essex County Council, WS Atkins, French Kier Anglia, Ruddocks, RF Thompson, Bourne Steel, Solaglas

Start: February 1999

Completion: October 1999

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.