Trusses hoisted for new Stansted Airport hangar

A pair of mobile cranes began hoisting the main trusses for a Ryanair hangar and flight simulator centre at Stansted Airport last week.

The purpose-built facility is capable of accommodating up to five Boeing 737 NG aircraft at any one time.

The tandem lift is a key stage in the £11m design and build project being undertaken for the low-cost airline by Kier Eastern, part of the Kier Group.

The scheme design, prepared by consulting engineering practice Equipment Solutions, measures around 128m X 58m and with a maximum height of approximately 25m. The cavernous interior will be supported by four structural steel trusses, designed and fabricated by Barrett Steel Buildings, of Bradford.

The first two trusses, which weigh 100 tonnes, were connected together on the ground before being hoisted into place using two 300 tonne-capacity mobile cranes from Peterborough Crane Hire - a Grove GMK 6300 and a Terex Demag AC350.

Kier Eastern project manager Mark Lockley explained: "Lifting the first two trusses as a pair provides us with a more stable structure to start with. We can then lift each of the two remaining trusses individually and connect them securely to the existing steel structure.”

Each truss provides a clear span of 124m, allowing maximum access space for aircraft. As well as aircraft maintenance, the giant hangar will house three storeys of workshops, offices and crew training facilities at the rear, including two flight simulators to be installed during the building programme.

Scheduled to finish on October 6, the 38-week programme also includes construction of an adjacent warehouse facility covering approximately 1,680 sq m.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.