Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Stretch of subway destroyed on 9/11 set to reopen

A STRETCH of New York's subway destroyed in the World Trade Center attacks is to reopen nearly a year ahead of schedule.

Commissioning tests are under way and trains are due to start running again on 15 September, four days after the first anniversary of the atrocity.

Joint venture contractor Tully/Pegno carried out the $92M (£60M) contract to rebuild the 430m stretch of tunnel which carried subway lines 1 and 9 under the WTC twin towers.

This was crushed under the weight of the collapsing structures. The firms worked 24 hours a day seven days a week to complete the job.

Work was carried out along the edge of the WTC site and the 'bathtub' foundation wall while recovery operations continued inside the site, and new tie-backs and wall sections were installed (GE March 2002).

The design, carried out inhouse by New York City Transit, kept to the original structural form dating from 1918, with the tunnel encased in concrete.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.