Davis Langdon

Sizewell B/Elean Data Campus/ESCO Brokerage

Sizewell B

Project description

This was the first and currently the only PWR nuclear power station delivering 1200MW to the national grid. Davis Langdon delivered independent cost consulting services for the civil and structural work; to time (8 years) and to budget (circa £3.6bn).

Start/finish dates

1987 to 1995

Challenges

■ Delivering this project with integrity to the relevant safety and environmental standards was paramount to its long term success.
■ Maintaining pace of coordinated delivery despite complex procurement of signifi cant supply chain (50 contractors and 3000 suppliers).

We believe in providing joined-up strategic thinking services that bring holistic solutions to the energy sector

Jon Dedman, Davis Langdon  

Elean Data Campus

Project description

A data centre campus where energy is generated, consumed and distributed effi ciently across multiple uses and technologies. Davis Langdon is providing independent cost planning to ensure delivery of a 40% reduction in electricity consumption and a 25% per annum reduction in tenant utility bills.

Start/finish dates

Ongoing

Challenges

■ Facilitate collaboration between multiple stakeholders to work in unison to achieve the increased effi ciencies and hence pass on savings stated.

■ Costing of interdependent utilities systems and associated infrastructure.

■ Identifying relevant measures and units to provide evidence of savings and reductions achieved.  

ESCO Brokerage

Project description

An innovative service is being developed to facilitate and manage the commercial aspect of creating an ESCO. They help all parties achieve a balance between competitive pricing and revenue generation.

Start/finish dates

3rd quarter 2009

Challenges

■ Creating an appealing investment that aff ords a good ROI.

■ Minimising the risk of becoming an energy supplier whilst maximising the revenue potential.

■ Brokering a balanced fi nancial model that satisfi es all stakeholders key issues.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.