Nimby councils hold up small windfarms

Local planning authorities are jeopardising the UK's bid to produce 15% of its total energy from renewable sources by 2020, it was claimed last week.

The government predicts it needs 14GW of onshore wind generating capacity as part of an overall renewables mix to hit the
EU 2020 target.

But, wind industry experts said weaknesses in the planning system are preventing onshore wind from delivering its target contribution. At present plans to build 7.1GW of capacity are stuck in the planning system.

This is more than the combined total capacity of schemes in operation,
under construction or with planning consent.

"Unfortunately it’s always the vocal minority heard by the councillors,
and they’re too easily influenced, and become heroes for saying ‘no’ to central government," said renewables firm Your Energy’s managing director Richard Mardon, speaking at the British Wind Energy Association's (BWEA) 30th anniversary conference in London last week.

The new Planning Bill is intended to speed up infrastructure planning applications by fast tracking projects through the new Infrastructure Planning Commission (IPC).

But proposals for wind farms with a generating capacity below
50MW will fall outside the IPC's remit and will to go through the
local planning system.

Mardon said councillors on planning authorities had to be
stronger in face of opposition to the project.

"Ninety per cent are in favour of windfarms or don't care either way,” he said.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.