NEWS IN BRIEF: Channel Tunnel

NEWS

PITTED AGAINST THE CLOCK: Hundreds of cubic metres of sulphurous smelling black Thames estuarine mud are currently being removed between diaphragm walls in a tunnel starter pit for the Channel Tunnel Rail Link's Thames crossing near Dartford. Amec/Spie has a £20M subcontract with Hochtief/Murphy for the pit and a 700m cut and cover approach for the tunnel on the river's south side as well as a similar 400m long north side approach.

The pit area must be ready in March for delivery of the first section of a Herrenknecht slurry head soft ground TBM which will make the first of two 2.5km long 8.15m diameter main drives.

A second machine head will be prepared on the south bank for the other bore, using the same back up train which will be brought back across the river.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.