New bed for a crib

Foundations - Making good a failing retaining wall in south Wales called for an unusual combination of foundation anchors.

Patients at Pontypridd's Dewi Sant Hospital in Wales have had the perfect vantage point for monitoring work to stabilise a 6m high railway retaining wall.

Masonry had fallen from the wall and earth had slipped from the slope above it, forcing Network Rail to take action. Main contractor Richards Construction and structural engineer Bradley Associates proposed a combination of a crib wall and rock anchors. Piling specialist Roger Bullivant was hired to install 250 Cintec anchors to improve cohesion. Forty rock anchors provide support for the wall and the upper slope.

Severely damaged sections of wall have been drilled using a hand -held diamond coring machine, with grids of holes created at 600mm centres for the Cintec anchors. Each anchor is formed from a 900mm length of steel tube, 12mm in diameter, and is wrapped in a fabric sleeve that expands to grip the wall when grout is injected under pressure through a small hole in the anchor's centre.

Completion of the Cintec anchors was followed by installation of two rows of rock anchors at a rake of 30infinity below horizontal to hold the wall in place. They extend to depths of between 5m and 7m through fill, dense gravels, sandstone and limestone. In areas of loose fill, steel casings were used to keep the bore holes open while anchors were installed.

Unstable rows of masonry at the top of the retaining wall were dismantled and a reinforced concrete beam cast in their place. The new concrete beam has been designed to accommodate a 2.7m high crib wall to prevent further erosion from the hospital garden.

The crib wall is timber backfilled with compacted stone.

Completion is due in January.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.