Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Morgan Est in Thames Water breakthrough

Thames Water linked its 9.3km ring main extension to the original 80km circular ring main shaft beneath London yesterday.

The £95M project to build Britain’s longest tunnel will boost the quantity of water that can be carried around the capital.

Morgan Est’s Project Manager Daljit Dhanda, said: “The entire team has done extremely well in delivering this tunnel. It has been a reliable drive and we have had good steady progress in often challenging conditions.

“The project has been undertaken in a quiet residential area with work continuing 24-hours a day, five days a week.

“Through constant monitoring of noise levels, effective mitigation measures and a professional disciplined workforce we have ensured the agreed constant levels were not exceeded and have minimised our impact on the local environment.

“The breakthrough itself went extremely well and is testament to the consistent dedication and hard work of our team,” he said.

The breakthrough by contractors Morgan Est completed the northern extension from Stoke Newington to Islington.

The southern section from Honor Oak to Brixton will complete next month.

Thames Water’s project manager for the northern extension, Rachel Whiteman, said: “Both  new  tunnels,  one  to  the  north and one to the south of the River Thames,  will  have  the  combined capability of carrying an additional 500M litres of water each day.” The extensions  are  long, driven by tunnel boring machine 45m below the surface.

The event happened yesterday after 12 months of tunnelling, which began at Thames Water’s Stoke Newington Reservoir in Hackney, and was watched by a select party of Thames Water and Morgan Est representatives.

The finished 2.6m diameter concrete-lined tunnel will link the water treatment plant at Coppermills with the Thames Water Ring Main ensuring greater resilience of London’s potable water supply.

In addition to the main tunnelling work, the contract involves the upgrade of associated services and the construction of two deep shafts to depths of 50m. The 4.5km length of tunnel connects these two shafts with further branch tunnels constructed at both ends to allow connection to the existing network. The diameter of the launch shaft is 10.67m and the diameter of the reception shaft is 7.5m.

The project is scheduled for completion in Spring 2010.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.