Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Metronet faces £700k fine for Waterloo & City delays

News

TUBE CONTRACTOR Metronet faces a fine of at least £715,000 after completing the £40M Waterloo and City Line upgrade 10 days late. Failure to open on time is another blow to the contractor's already tarnished reputation.

The project was intended to counter Metronet's poor track record by showing that it could deliver projects on time and to budget.

'Yes, there was a lot riding on our reputation on this, but what we've built is of good quality.

It's just regrettable that it's a few days late, ' said a Metronet spokesman.

London Mayor Ken Livingstone said this week that he was not surprised that the project had been delivered late.

'We didn't believe Metronet would open the line on 1 September. But being just one week late on a five month contract is a breakthrough - we expected them to be two or three months late.'

But Livingstone warned that if Metronet's performance did not improve by the end of the year then he would begin talks with the government to resolve the situation.

Metronet paid London Underground (LUL) £3M so it could carrying out the work during a e month closure of the line, instead of doing it piecemeal during overnight engineering hours (NCE 9 March).

This model was to have been used across other sections on the network.

Service on the Waterloo and City Line was supposed to resume on 1 September, but will now be pushed back to at least 11 September while nal line testing and driver training takes place.

The Metronet spokesman said that problems with signalling, encountered during the commissioning phase, had caused the delay.

'Signalling is always a risk because you can only test it when the whole track has been completed.

'It was always going to be a tight programme with little slack, ' he said.

The line upgrade involved replacement of 4.3km of bullhead rails on longitudinal timber sleepers with at bottomed rails on concrete cross sleepers. A new signalling system was also installed to allow trains to run closer together.

Metronet's poor performance has been under scrutiny by client LUL since its Public Private Partnership contract was signed in 2003.

In July LUL reported that the contractor had only completed 14 out of 35 stations, all of which were delayed (NCE 27 July). The client has since issued a formal warning for poor progress on station upgrades - which could lead to withdrawal of the contract.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.