Messina: the challenges

News

The bridge itself accounts for a surprisingly small £1.2bn of the total £3.1bn price tag. The crossing will link into road and rail networks on either side via a combined 40km of new roads and railway, costing £1.5bn.

More than 30km of the new road and rail infrastructure will have to be built in tunnel. Relatively little ground investigation was done before tenders were invited, leaving bidders without detailed information against which to draw up designs.

The area is an earthquake zone, and Sicily sits on a different tectonic plate to Calabria. Yet seismic information was also lacking in tender documents, claimed Strabag head of civil engineering Martin Ullrich.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.