Phoenix from the floods

Workington’s Northside Bridge reopened last month, three years after the original structure collapsed. Steelwork played a pivotal role in re-spanning the River Derwent.

workington3

NORTHSIDE PERMANENT BRIDGE REPLACEMENT

The devastating floods of 2009 will not be forgotten in the north west of England for a long while. Human casualties aside, the effects are only now being completely rectified and the opening of Workington’s Northside Bridge represents the last major hurdle on the way to Cumbria’s infrastructure recovery.

The original bridge collapsed and was swept away on 20 November 2009. Within weeks a temporary bridge was erected but last month, after three years, a new permanent crossing spanning the River Derwent and the A596 was opened.

The new 152m long, three span composite steel bridge has been erected in the same position as the former structure. It is supported on concrete piers with bored pile foundations and clad in sandstone some of which was recovered from the original bridge.

“Steel offered us a number of benefits, one of which was speed of construction,” says Capita Symonds project manager Alan Webb.

Main contractor Birse Civils started on site during August 2011 and completed the programme in a little over 14 months, achieving one of the client’s main objectives - namely having the new bridge open within three years of the old original structure’s demise.

” Steel offered us a number of benefits, one of which was speed of construction,”

Early works for Birse included the removal of the original bridge’s foundations and locating the service diversions. For the foundations a total of 72 bored piles were installed to a depth of 26m.

The structure’s two piers are positioned on both river bank.

This negated a lot of potentially hazardous working over and in water and also resulted in a quicker construction programme.

But it was not the only reason for this design as Cumbria County Council project manager Jason Dixey explains: “During public consultations about the construction of the bridge, local people made it clear they wanted something that looked robust, and bearing in mind what happened to the old bridge, piers in the river did not seem appealing.”

Mabey Bridge fabricated, supplied and erected the steelwork package in three phases.

The structure was split into three segments for the construction programme.

The northern side of the bridge was erected over one weekend in February, followed a month later by the installation of the southern part.

The northern side of the bridge comprised of six pairs of braced girders, three 30m long pairs and three 23m long pairs all incorporating the bridge’s haunch.

Spanning from river bank abutment, onto a pier and then over the river, temporary trestles supported the structure between the pier and the abutments during the erection process.

workington1

Northside Bridge Workington

“Once all of the girders were installed and the cross beams had been welded into place the trestles were removed as the steelwork was then stable,” says Birse Civils site manager Phil Dilworth.

Two mobile cranes were utilised for this operation, one 700t capacity unit to do the three girder lifts, and a smaller 60t crane to install the cross beams.

The northern section spans the A596 road, and, in order to install the steelwork, the project team had a weekend possession in place from a Friday night until the following Monday morning.

So successfully and quickly was the steelwork erected that the road was able to reopen on the Sunday lunchtime. - earlier than anticipated.

In a similar procedure the southern section, which is identical to the north, was then erected last April, leaving the middle 46m long mid span to be installed during May.

In order to avoid working in and over the river, the installation of the middle section was done slightly differently.

“We couldn’t put temporary trestles in the river so we had to weld the six pairs of girders into three long sections and lift them into place with a much bigger crane,” says Dilworth.

Mabey Bridge brought six pairs of small girder sections to the riverside site to make the 46m long centre span girders. Over a period of four weeks they were welded into the required longer lengths.

workington2

The cantilevering formwork - used to form the deck - was also installed on the steelwork before the lifting process, minimising even further the amount of work that would have had to be done over the river.

Birse provided an on site assembly yard adjacent to the southern abutment for this work.

Each of the three lifts needed to erect the bridge’s mid span weighed 160t, 88t of steel and the remainder consisting of formwork.

To do this work a Demag cc2800-1 crawler crane was needed. This unit has a lifting capacity of 800t, a 60m long boom, a 180t counterweight and took two days to assemble on site.

“Installing the final sections of the bridge girders was a key moment in the delivery of the project.

“It was also significant in this case as it re-established the connection between the north and south banks of the River Derwent,” says Dilworth.

Project team

Project: Northside Bridge, Workington
Main client: Cumbria County Council
Main contractor: Birse Civils
Structural engineer: Capita Symonds
Steelwork contractor: Mabey Bridge
Steel tonnage: 980t
Project value: £11.7M

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.