Phi gets stuck into M60 retaining wall

Keller UK’s retaining wall division Phi Group and Keller Geotechnique are involved in ground retention works on a 6ha site next to the M60 motorway at Stockport.

The £350,000 contract for main contractor VolkerFitzpatrick involves installing 460 soil nails of between 7m and 11m in length on a 65˚ slope over an area of 450m2. Phi is also installing its Textomur geotextile over 1,380m2 of the slope using reinforcement between 3m and 6.5m long.

The site is being jointly developed by Helical Bar and Chancerygate. It will house industrial and warehouse facilities. Phi’s work started in August and is due to be completed this month.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.