Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Milestone for Bank as massive truss installed

Bank truss ny 180719 69

A significant milestone has been reached in the upgrade of Bank Station in London as a massive temporary truss is installed to allow the construction of its new eight-level deep station entrance.

Robert Bird Group (RBG) said the new truss was an innovative alternative approach to support the slabs which would eliminate the health and safety risks associated with using a plunge column technique within the low level 20m deep shaft.

“The use of a traditional plunge column in this position would have compromised the construction of the lower level slabs within the sprayed concrete lining shaft at the bottom of the station box with reduced working space,” said RBG managing director Simon Nicholas.

“Also, the presence of the existing DLR [Docklands Light Railway] structures beneath the box restricts the capacity of plunge piles. The team overcame these issues by designing an innovative temporary truss to hang the station slabs, enabling the top down construction.”

The new truss supports four levels of basement slab within the 18.5m deep piled basement structure and will now enable the entrance of the station to be constructed.

The 100t steel truss has a jacking system which is used to counteract the “complex” response from incremental load of the slabs as they are progressively constructed and the progressive excavation below during the staged top down construction sequence. The truss had been designed to resist 1,800t at ultimate limit state (ULS).

At present one of the four slabs has been constructed, with the remaining three constructed in the coming months.

The truss had been conceived in collaboration with Dragados, and fabricated and installed by Byrne Bros as part of its overall concrete station box package. RBG is also responsible for the trusses on-going monitoring and jacking.

The monitoring regime will ensure its design assumptions are validated, reducing project risk and ensuring slabs remain parallel and end in the correct final position.

Like what you’ve read? To receive New Civil Engineer’s daily and weekly newsletters click here.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.