Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Government could strip Crossrail of delivery if costs further increase

3125647 3124652 crossrailfarringdonsign

The Department for Transport (DfT) could take over the delivery of Crossrail if costs continue to escalate, it has emerged.

A clause in the 2008 Crossrail sponsor agreement states that the department has the power to take over the running of the project under certain circumstances, including in the case of cost increases.

In August, the project’s bosses announced that it was to delay the opening of the central section of the line until the end of 2019, up to a year after the planned opening date of December this year.

It also previously announced a cost increase of £600M, taking the total cost of the project to £15.4bn, citing “engineering challenges” as the reason for the overrun.

It is unclear whether the DfT plans to use the powers, although a spokesperson for project promotor Transport for London (TfL) confirmed that it was working closely with the government to come to a resolution.

A TfL spokesperson said: “We are committed to ensuring the Elizabeth line is completed as quickly as possible and we are working closely with Crossrail Ltd and government on delivering this.

“Crossrail Ltd is working to establish what the additional impact on funding from the revised delivery schedule will be and discussions continue with Government on how to deliver any financing that may be required.”

When the cost overrun was announced, the DfT said the additional funding would be made available by TfL, Network Rail and the DfT.

It said it would contribute £150M to the project, with TfL stumping up another £150M. Around £290M would then be made available for the completion of the works on the surface network by both the DfT and Network Rail.

The DfT said it would not comment on its plans.

Like what you’ve read? To receive New Civil Engineer’s daily and weekly newsletters click here.

Readers' comments (1)

  • Philip Alexander

    Fancy "discovering" a cost increase of £600 million all in one go!!!!!
    Any competent engineer would have been keeping tabs on incremental cost increases as they went along and advised their client accordingly, who of course would have advised central government as they went along. This is a perfect example of those incompetents keeping the information to themselves so it's too late for those holding the budget purse-strings to ask for cost savings. It's disgraceful and heads should roll. But no, they'll all get gongs in the NY honours and told what a good job they are doing. Not to mention being given huge bonuses all out of the public purse.
    Disgraceful.

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.