Freight Expectations

Belgium’s biggest civil engineering project is designed to add major freight capacity to the port of Antwerp. Declan Lynch meets the project team constructing the challenging 16.2km Liefkenshoek rail link.

Transport links to the expanding Port of Antwerp have reached saturation point.

The port’s right bank has good transport links but no room to expand.

The left bank, separated by the River Schelde, has room to develop but rail routes are constrained by a bottleneck further south.

To enable the port’s growth, a new rail link must be built beneath the port to connect the two sides.

However, it is difficult ground to tunnel in and expensive to build.

As a result, Belgium’s railway maintenance manager, Infrabel, has joined forces with consortium LocoRail to finance and maintain the link, while construction will be managed by another consortium, LocoBouw (see box right).

Currently, all road and rail traffic passes through the Kennedy Tunnel to the south of the port.

When the Liefkenshoek link opens in 2014 it will just be used for freight trains and allow direct access to the port.

This will remove the bottleneck at the Kennedy Tunnel, freeing up passenger rail services between Amsterdam and Brussels.

The first stage of the 16.2km link is an open cutting which connects to the existing - and now renovated - 1.2km cut and cover Beveren Tunnel.

This was built in the 1970s prior to construction of the Waasland Canal in anticipation of a transport link that never came to fruition.

“Depth of the tunnel is very important - too high and the tunnel will float, too low and it will pass through the clay”

Then there is a second, smaller section of open cutting before the next, and biggest part of the project, which is the two single-track 6km bored tunnels underneath the River Schelde and a canal dock (B1/B2).

It cuts through challenging ground conditions with a very small margins for error.

The open cuttings will need diaphragm walls, which are down to a maximum 40m depth.

Tunnellers will be passing underneath two major watercourses in a sandy layer, but just above a clay layer.

“Depth of the tunnel is very important - too high and the tunnel will float, too low and it will pass through the clay,” says LocoBouw director of works Alex Vandemeulebroecke.

Engineers decided to use an 8.39m diameter Herrenknecht pressure balanced tunnel boring machine (TBM).

Once completed the internal tunnel diameter will be 7.30m.

With only 600m of the 6km tunnel in clay, Vinci Construction Grand Projets designed it for the fine sand that covered the rest of operation.

To begin boring, tunnellers inject bentonite at the front of the cutterhead, which makes a watertight membrane.

The pressure is controlled by the amount of bentonite pumped in.

“It’s not that easy,” adds Vandemeulebroecke. “You must be careful, if there’s too much pressure then there would be a blow-out.”

The first TBM, called Fanchon, began its operation in February 2010, with the second, Bobette, starting its journey two months later.

Tunnelling moves along at an average of 16m a day, with the Fanchon TBM slower to allow the cross passages to be completed.

Tunnel_60_photo_Philippe_van_Gelooven

More than 800,000m3 of spoil will pass through the two machines, which is treated on site and then used to help create sea defences close to the port.

As the TBM pushes through the earth, a seven segment concrete ring is pushed into position.

A total of 53,000 pre-fabricated concrete segments, which are being delivered to site at a rate of 1,200 a week by train from Germany, will be used in both tunnels.

Tunnelling through the sand has been relatively straightforward, but underneath the River Schelde, the TBM passes within 10m of the riverbed.

The bottom of the river is disturbed ground, which means it is not as dense as naturally formed ground.

Furthermore, as it is a tidal river, the hydrostatic pressure changes by up to 4 bar of pressure around the tunnel.

“Water pressure was a major issue. Every hour we made checks,” says Vandemeulebroecke.

Engineers needed to stabilise the soil underneath the canal dock so that the TBM could pass through and so in May 2010, 25,000m3 of slow-setting mortar was poured into the canal basin.

The operation involved four concrete mixing plants, four pumps and a total of 240 people.

In July 2010, a further 20,000m3 of rapidly setting concrete was poured in the same conditions.

This concrete serves as a counterweight during the boring operations and will protect the tunnels from any ship impact.

“The tunnels pass just a few metres below the reconstructed canal bottom,” says LocoBouw tunnel director Lionel Suquet.

Between the bores are 13 shafts and eight cross passages.

“It takes about 250 days from start to finish to construct a cross passage”

These have been constructed, in all but one case, by freezing the ground beneath the tunnel.

“It takes about 250 days from start to finish to construct a cross passage,” adds Suquet.

Pipes are inserted through the earth to the other tunnel bore filled with brine.

This freezes the ground, enabling engineers to excavate between the two bores.

Once the engineers have broken through to the other bore, a steel lattice arch is placed in the hole, and concrete pumped in.

During the next stage, the passage is lined with a waterproof membrane, after which a steel rebar cage is fitted and poured with concrete to form the platform.

The cross passages are placed every 250m underneath the river, and every 300m along the rest of the tunnel.

“They will only be used by the train driver because it’s a freight only tunnel,” adds Suquet.

Once the tunnel is completed, LocoBouw will install a state-of-the-art active fire suppression system along both tunnels, which spray foam in the event of a fire.

Completion of the second tunnel is expected in July, with construction finished in mid-2013.

Infrabel will begin installing the railway infrastructure, such as the tracks, signalling and overhead lines, from 2012 until its opening in 2014.

All being well the Liefkenshoek rail link will open in mid-2014 and LocoRail will be responsible for the maintenance of infrastructure until 2051.

Tunnel_70_photo_Philippe_van_Gelooven

Contract Details

To enable construction of the project infrastructure operator Infrabel has signed a 42.5 year design, build, finance and operate contract with the LocoRail consortium (French, Belgium and Dutch concessionaires Vinci Concessions, CFE and Bam PPP Investments) worth E841M (£730M).

Construction of the £522M project is being handled by sister firms of the concessionaire, collectively called the LocoBouw consortium and consisting of Vinci Construction Grand Projets, CFE subsidiary MBG, and Bam subsidiaries Cei-de Mayer and Wayss & Freytag.

While PPPs are common in the UK, they are not in Belgium and this is the first major one in the country.

 

Key Facts

Project team

Client: Infrabel

Project consortium: LocoRail - Vinci Concessions (25%); CFE (25%); Bam PPP Investments (50%)

Construction consortium: LocoBouw - Vinci Construction Grand Projets (25%); MGB (CFE subsidiary) (25%); Cei de Meyer (Bam subsidiary) (25%); Wayss & Freytag (Bam subsidiary) (25%)

Tunnel Boring Machine

Type: Herrenknecht pressure balanced TBM (slurry shield)

Total length: 102m

Cutting shield diameter: 8.39m

Cutting shield length: 11.7m

Cutting wheel power: 1,100kW

Main quantities

Diaphragm walls: 120,000m2

Steel: 40,000t

Concrete: 400,000m3

Earthworks: 3,000,000m3

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.