Crossrail construction timeline

A chronological view of the Crossrail project

Canary Wharf 2009 to 2016

  • Dec 2008 Enabling works start
  • May 2009 Construction starts
  • 2016 Works complete

Tottenham Court Road 2010 to 2016

  • Jan 2009 Enabling works start
  • Early 2010 Construction starts
  • 2016 Works complete

Farringdon 2010 to 2017

  • July 2009 Enabling works start
  • Early 2010 Construction starts
  • 2017 Works complete

Paddington 2009 to 2016

  • Sep 2009 Enabling works start
  • Mid 2010 Construction starts
  • 2016 Works complete

Whitechapel 2010 to 2016

  • Early 2010 Enabling works start
  • Early 2011 Construction starts
  • 2016 Works complete

Woolwich 2011 to 2016

  • Early 2010 Enabling works start
  • Early 2011 Construction starts
  • 2016 Works complete

Bond Street 2011 to 2016

  • Mid 2010 Enabling works start
  • Mid 2011 Construction starts
  • 2016 Works complete

Liverpool Street 2011 to 2016

  • Late 2010 Enabling works start
  • Late 2011 Construction starts
  • 2016 Works complete

Custom House 2012 to 2014

  • Early 2012 Enabling works start
  • Late 2012 Construction starts
  • 2014 Works complete

Stepney Green shafts To Pudding Mill Lane 2009 to 2016

  • Early 2011 Works start
  • Mid 2013 TBM launch
  • 2014 Works complete

Limmo Peninsula Towards Farringdon 2010 to 2016

  • Late 2010 Works start
  • Late 2011 TBM launch
  • 2014 Works complete

Limmo Peninsula Towards Custom House 2010 to 2014

  • Late 2010 Works start
  • Late 2014 TBM launch
  • 2015 Works complete

Fisher Street shaft and crossovers 2011 to 2015

  • Mid 2011 Works start
  • 2015 Works complete

Plumstead Towards North Greenwich 2011 to 2014

  • Early 2011 Works start
  • Mid 2012 TBM launch
  • 2014 Works complete

 

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.