CLIENT GUIDE: MANCHESTER AIRPORT

The airport's £1bn growth plan to 2015 will be achieved largely by extending and rationalising its three terminals. Major opportunities include:

Terminal 1: Transfer lounge and baggage handling facilities. £90M Terminal 2: 50% expansion on two levels. £200M Terminal 3: 25% expansion.

£50M Ground transport interchange:

£60M conversion of rail station to multimodal use. £27M shell and core contract already let to Skanska. £15M fitout to be tendered separately Manchester Metrolink: £90M, 21km extension of tram system from city to airport.

Starts 2003. £10M being funded by airport but contracts let through Greater Manchester Passenger Transport Executive Maintenance and refurbishment:

£100M spend to 2015. Over 70 contracts to be let, mostly design and build bids from select list. Few frameworks Retail outlets: £50M.

Long term plan to convert the ground transport interchange to a through station with an 8km, £200M rail link to the West Coast Main Line.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.