HEX: the cost

Planned

Balfour Beatty's original tender value: £60M

Trial tunnel cost £1.1M

Unplanned

Cost of collapse to BAA £35M

Cost of collapse to Balfour Beatty £35M

Cost of collapse to BAA and Balfour Beatty's insurers £100M

Cost of airport disruption £50M

Cost of shutting down JLE sites as a safety precaution £200M

Fine for Balfour Beatty £1.2M

Fine for Geoconsult£0.5M

Cost to Geoconsult of expert witness report £0.125M

HSE prosecution costs £0.88M

Total extra unplanned cost £422.7M

(Excluding cost of precautionary two week London Underground Piccadilly line closure, Balfour Beatty's legal costs and Geoconsult's legal costs)

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.