Grinding out a result

As budgets get squeezed, different approaches to cost-effectively extending the life of roads are being examined by the Highways Agency. One of these is diamond grinding and grooving. NCE reports.

Used for many years in the US, diamond grinding and grooving is being increasingly used on this side of the pond. And no wonder - the process can restore the surface performance of concrete roads at less than half the cost of overlaying with asphalt.

As well as bringing as cost savings, the process is fast, has a lower carbon footprint than an asphalt overlay, and provides a road surface that is noticeably quieter than untreated concrete as traffic driving over a textured surface emits less noise than a smooth surface.

Grinding and grooving

Grinding and grooving involves plant equipped with closely-spaced diamond-tipped saw blades that cut drainage and traction grooves into the road surface.

“Reductions in noise levels compared with a smooth concrete surface with traffic at 30 to 50mph range from 4dBA-6dBA. At higher speeds noise reduction is even more noticeable.”

David Jones, Britpave

With grinding, 3mm to 10mm of the concrete pavement is treated to leave a level, high-performance riding surface. The closely spaced grooves left after grinding provide a high level of texture and friction.

The same technique and plant is used for diamond grooving. Whereas the purpose of grinding is to restore ride quality and texture, grooving is generally used to reduce hydroplaning by providing channels for water drainage.

The main difference between grinding and grooving is in the distance between the grooves - about six times greater for grooving.

Introduced into the UK by Concrete Cutters (Sarum), in partnership with UK abrasives company Tyrolit, the diamond grinding technique is half the cost of overlaying concrete with asphalt, is much faster and requires considerably less investment in capital plant.

Recent projects

Last year, the Highways Agency carried out a series of grind and groove trials at Alconbury Airfield, Cambridgeshire, between the A318 and A1114 junctions on the A13 Chelmsford bypass, Essex, and on the A12 Chelmsford bypass. Further trials have been carried out on 1.61km of the A12 Kelvedon, in both directions, 745m of the A12 Chelmsford northbound and 1km of the A11 Ketteringham northbound.

A major maintenance project on the A14 near Ipswich has also used the technique.

Early indications from accelerated wear tests are that the surface is durable and will retain its skid resistance and noise attenuation characteristics for many years, says Britpave director David Jones. “There has been a significant improvement in skid resistance of 54%. Reductions in noise levels compared with a smooth concrete surface with traffic flowing at 30 to 50mph range from 4dBA to 6dBA. At higher vehicle speeds the noise reduction is even more apparent,” he says.

It is anticipated that the results of the TRL study will be published later this year.

The first major project on the A14, involving four 6km lanes with a total area of 125,000 m2, was successfully completed in May. The main contractor was VolterFitzpatrick and the scheme was carried out within Highways Area 6 and was supervised by Atkins.

Jones says experience in California, a pioneer of the grind and groove technique, has found that while asphalt overlays typically last eight to 12 years, the average life span of a diamond ground concrete surface is up to 17 years and a pavement can be diamond ground up to three times without significantly affecting its structural performance.

Other benefits include the fact that the process can be carried out during off-peak hours with short lane closures and without encroaching into adjacent lanes. Grinding one lane does require grinding of the adjacent lane, which may still have acceptable surface friction and drainage and the clearances underneath bridges are not affected.

It is estimated that there are nearly 1,350 lane kilometres of concrete roads in the UK that need attention. With its considerable potential cost savings and long-term performance benefits, grinding and grooving offers the enticing possibility of its being used on new build and major reconstruction road projects. This has successfully been done in the United States and, in a time of cutbacks, could result in concrete roads making a UK comeback.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.