Gently does it

Cover story

Stripping the radioactive core from the UK's experimental Windscale advanced gas reactor is little more than 'scrap business,' says engineering manager Stephen Haslam.

But the demolition job is no ball and chain affair. The complexity of handling wastes safely means work inside the landmark 'golf-ball' started in 1981 and has been advancing at a snail's pace.

Nor are there materials to be reclaimed and sold on. When the project ends in 2005, the gain, it is hoped, will be to have proved to a nuclear- wary public that the atomic genie can be stuffed back into its bottle, or at least into the ground.

The UK Atomic Energy Authority, facility owner and project client, started building the prototype advanced gas reactor, known as WAGR, in 1957. The facility, completed in 1961, was designed as a research facility for the development of new fuels. Little thought was given to how it should be taken apart, Haslam observes.

'The reactor is incredibly well built, but taking it apart was someone else's problem,' he says. 'At the time, the issue was to start testing fuels.'

Construction practices have also changed in the 40 years since WAGR was built. Despite high build quality, design changes made during construction were poorly documented. 'We are suffering from iffy drawings,' states Haslam adding that in some cases drawings have vanished entirely.

The £80M contract to strip out the reactor's contents involves standard civil engineering techniques. However, working with toxic materials in a confined space calls for meticulous planning and robust methodologies. Safety is paramount: work is vetted by industry regulator the Nuclear Installations Inspectorate and parent body the Health & Safety Executive.

Haslam says of the nuclear energy industry as a whole: 'If anything is not safe, it is now recognised that's the end of business.' Lengthy periods of testing are required to make sure solutions are failsafe. Meanwhile, the long lead-in times and the creeping pace of work means any miscalculations have a bad impact on the project's critical path.

WAGR's reactor core is contained within a 6.5m diameter, 13.1m high steel pressure vessel, in turn isolated inside a 1.5m thick reinforced concrete biological shield. It is here that work is now focused.

Prime contractor for the project, BNFL Magnox, carries full financial risk. It has let 10 fixed price subcontracts through competitive tender. The first of these, for tooling and methodology, was awarded to Entech, a joint venture between contractors Strachan & Henshaw and French firm SGN, in 1997.

Human contact with the contents of the pressure vessel is out of the question. A robotic arm with a 14m reach is used and can be fitted with tools including gas cutters, shears and grabs. It will be lowered on a mast as work advances. Two cranes equipped with grabs allow operators, viewing the site via video, to manhandle waste out of the pressure vessel and into the adjacent chamber, where it is packed into steel baskets. These baskets are then lowered to an assaying chamber where their radiological load is measured before being incarcerated in giant reinforced concrete boxes.

Supplied by Tarmac, the boxes measure 2.2m by 2.2m by 2.4m externally, with an internal volume of just 1.4m2. Ordinary concrete provides adequate shielding for low level waste, says Haslam. Higher levels of protection are delivered by adding magnetite, an iron oxide compound, to the mix.

Waste material is grouted into the box with a high workability mix of Ordinary Portland Cement and pulverised fuel ash before the box is sealed. Low level waste is transported to the nearby Drigg storage facility. It is calculated the entire decommissioning project will generate 137 low level boxes.

Intermediate level waste, with a half life of between 20 and 600 years, is being stored on site pending delivery of a permanent repository for hazardous nuclear waste. Some 220 boxes of waste are expected to arise. The on-site bunker has a design life of over 100 years.

An initial 'mop up' operation to remove loose material from inside the pressure vessel has already been carried out. Work has just got under way to cut up and remove the hot gas manifold, or 'hot box', sitting above the core.

When the reactor was operational, gas was pumped up through the core, where it was super-heated. The hot box channelled the gas to four heat exchangers. It is built from 30mm thick carbon steel, and measures 5m in diameter by 1.2m high.

During preliminary decommissioning in the early 1990s the fuel channels were randomly chopped off above the hot box. To break the structure into manageable, 1m2 plates, it is now necessary to cut the channels flush with the hot box top surface. A plasma head attached to the robotic arm is being used to cut each channel internally.

Later this year subcontractor Nuclear Services Group will start work on removing the steel restraints binding the reactor's graphite core structure. Though it generates more particulate debris than cutting with a flame, these will be ground off.

Haslam explains: 'NSG was proposing to remove the bands using oxy-propylene cutting, but on graphite that is not desirable. If you subject graphite to heat over long periods, for instance in a reactor core, it retains energy. And if you heat it again suddenly, it relieves itself of that energy.' Fire is a real, but avoidable, danger.

The graphite core will also contain radiologically 'hot' Caesium 136 and Carbon 14, which are long-lived and highly soluble. It will be classed as intermediate level waste and placed in the controlled on-site environment.

But perhaps the most challenging element of the decommissioning project will be removal of the pressure vessel structure. Entech will have to cut the 102mm thick steel with an oxy-propane torch. However, tests have shown that the 200mm asbestos insulation coating the vessel reflects all but the hottest flames, and iron particles will be added to the gas mix.

Removal of all hazardous reactor structures is scheduled for completion by 2005-6, leaving just the biological shield and the outer membrane. Providing operations are glitch-free UKAEA and BNFL will have developed some leverage for assuaging public anxiety about nuclear energy.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.