Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Femern finally opts for tunnel crossing

Fehmarnbelt Crossing promoter Femern yesterday confirmed it would recommend the tunnelled option over the bridge proposal, despite recently lauding the benefits of the latter.

It said that an immersed tunnel would entail fewer risks in both the construction and operational phases than a cable-stayed bridge, despite the bridge being called “iconic” by the firm.

The technical risks of executing the two projects - surrounding environmental impact, navigation safety and construction cost - were the key factors in opting for the tunnel. But the decision remains provisional pending an Environmental Impact Assessment (EIA).

A final political decision on which of the two will be selected will be made in early 2011. It is anticipated that the preferred solution will form the basis for the project application to be submitted to the German authorities.

A specially enacted construction act will then be formed in Denmark and subject to approval by the German authorities.

Contracts for the construction work are not expected to be signed until 2014. It will be up to the contracting firms to organise the work, including the location of the large production sites for manufacturing bridge or tunnel components.

Femern said it had assumed that a large proportion of the steel structures for a bridge would be constructed in the Far East (possibly China) while tunnel components would be produced locally owing to their great weight. On account of the risks entailed by sea transportation of such large components, Femern said that production of concrete components should ideally be sited up to 120km from the route corridor. A more distant siting may also be considered if the contracting firms conclude that this would be more financially competitive overall.


Technical risks

A cable-stayed bridge across the Fehmarnbelt, with two free spans of 724m each, would be the largest spans ever constructed for either road or rail traffic. Compounded by the high shipping traffic in the area, this would pose significant risks in the construction phase in terms of cost overruns, delays and industrial accidents.

An immersed tunnel will also present considerable technical challenges during the construction phase, as a result of the intensive shipping traffic in the Fehmarnbelt. However, unlike a bridge, an immersed tunnel will not entail as many technical operations which push the limits of what has been done before. Essentially, the procedure will be the same as it was for construction of the Øresund Fixed Link’s immersed tunnel under the Drogden Channel, only many more times over and at far greater depths, such as up to 30m to 40m in the Fehmarnbelt against approximately 10m in the Øresund. The Fehmarnbelt tunnel will be just under 18km long, while the Øresund Tunnel is around 4 km long.


Environment

Both a cable-stayed bridge and an immersed tunnel would impact the marine environment in the Fehmarnbelt. The preliminary conclusion is that a bridge would have slightly more significant permanent environmental impacts than an immersed tunnel. However, the nature of these impacts does not, from a purely environmental perspective, preclude a bridge.

A number of the environmental impacts of a fixed link would be on Natura 2000 sites. In such instances, EU legislation prescribes that the least intrusive alternative must be selected.


Navigation safety

In the interests of navigation safety, a tunnel clearly poses fewer risks than a bridge. The Fehmarnbelt is a heavily trafficked stretch of water with 47,000 vessel transits per annum (2006), including many tank vessels. In the coming years, shipping traffic in the Fehmarnbelt is expected to increase substantially to approximately 90,000 vessel transits in 2030.

However, risk analyses for a bridge show that, from a vessel perspective, navigation safety would be improved in relation to a situation with no bridge and continued ferry crossings. This would require a cable-stayed bridge with two navigational spans of at least 724m each, and the implementation of permanent, radar-based vessel monitoring in the form of a Vessel Traffic Service (VTS) system covering a range from the south end of the Great Belt to the Cadet Channel.


Financial factors

In financial terms, there is very little difference between the two projects. The construction estimate (2008 price level) for an immersed tunnel is €5.1bn (£4.27bn) and for a cable-stayed bridge £4.35bn.

But assessment of the overall cost of each of the two projectswould take into account the construction time and the cost of operation and maintenance. The construction time for the tunnel is estimated at six and a half years, and for the bridge, six years. The cost of operation and maintenance is slightly higher for a tunnel than for a bridge.

The payback time for the two projects would be essentially the sam - approximately 30 years for the coast-to-coast project. This means that, from an overall financial perspective, there is no difference between bridge and tunnel.

 

Readers' comments (2)

  • I am so happy for the tunnel option to have been chosen as the preferred option, considering it came from well behind the bridge option. Having worked (albeit briefly) on this project myself, and having rubbed shoulders with the Who-is-Who in the world of tunnel design, I am humbled to have my fingerprints on this potentially the most iconic and most daring construction projects of the twenty first century. I am looking forward to seeing the project on National Geographic!

    Unsuitable or offensive? Report this comment

  • Charles Slater

    There must be a mistake in the English of the first sentence of Technical Risks. Should it read " .... the longest combined road and rail link ever constructed ...." ? More simple data may be needed.
    Japan's Akashi Kaikyo road-only suspension bridge has a main span of 1991 m and Hong Kong's Tsing Ma combined road-and-rail suspension bridge has a main span of 1377 m

    Charles Slater

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.