Edinburgh Tram land orders to be extended due to delays

The Scottish Government has laid before Parliament two orders to extend the time limits for the City of Edinburgh Council to compulsorily acquire the land needed to complete its trams project.

The council requested the extension of these powers under provisions in the Edinburgh Tram Acts authorising construction. The extensions are needed due to disputes and delays which have meant that the project is now unlikely to open until at least 2013, two years late.

The government said that the new orders would enable the project to move forward after resolution of the current contractual dispute between the council’s transport agency tie and the construction consortium lead by Bilfinger Berger. 

Transport Minister Keith Brown said: “The Scottish Government’s position on Edinburgh trams is clear. We opposed the project, but in June 2007 the Scottish Parliament voted that we provide funding to a maximum of £500M. The project is and always has been the responsibility of City of Edinburgh Council.

“We want to ensure that nothing stands in the way of delivering trams for the benefit of the people of Edinburgh. Given the delays caused by the current contractual dispute not extending these powers of land acquisition would seriously compromise the Council’s ability to complete the project.

“The Scottish Government is simply not prepared to place the people of Edinburgh and the public purse in such a position.”

Brown also reiterated the Scottish Government’s commitment to assist the Council in resolving the project’s current difficulties.

“With mediation due to start next month (March) it is not the right time to be discussing substantial changes to the governance of the project. However, we want to ensure that every opportunity is taken to resolve this long running dispute so that a tram service can be delivered in Edinburgh, and have agreed that Transport Scotland will take part in the mediation process,” he said.

The two Acts (the Edinburgh Tram (Line 1) Act 2006 and the Edinburgh Tram (Line 2) Act 2006) provide for the council to construct and operate the tram line between Edinburgh Airport and Leith. The powers of compulsory acquisition were granted for an initial period of five years and are due to expire in April and May 2011 for line two and line one respectively.

An amalgamation of the two proposed lines is being constructed running from Edinburgh Airport to Newhaven, although it may only reach Princes Street in the first stage. The Line 1 bill provided for a loop from St Andrews Square , along Leith Walk to Leith , west to Granton, south to Haymarket and back to St Andrew Square along Princes Street to be constructed, while Line 2 was for the line west from Princes Street to Edinburgh airport.

The powers can be extended for a further period by Order of the Scottish Ministers following an application from the local authority. The extensions provided by the Orders are for five (Line 1) and ten years (Line 2) and come into force on 1 April 2011.

As a result of the delay arising from the current contractual dispute, it would otherwise not be possible within the time remaining to complete the acquisition of all the land required - a small amount of land between the airport and St Andrew Square and some larger parcels of land, most of which are in the north-east part of the City.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.