Dubai shiplift launcher saves on costs

NEWS

WORK IS to start on a rare hydraulic shiplift in Dubai later this summer after contractors put in bids a fortnight ago.

The £12M lift for client Dubai Drydocks is believed to be only the second of its type, said Stuart White, project manager with designer Royal Haskoning.

The only other is in Portugal.

Dubai Drydocks is ordering the lift to enable construction of huge 360m long by 60m wide oil storage ships, which are increasingly being moored on offshore oil fields as tanks.

Such ships are conventionally built on a slipway and launched by sliding them into the sea.

But Dubai Drydocks is opting for the hydraulic lift because it will be cheaper to construct and maintain, said White.

The lift will comprise a 14m deep basin adjoining the fabrication yard, which is 5m above sea level. The whole complex will measure 130m by 130m.

Basin and fabrication yard will be surrounded by a 5m high sheet piled and mass concrete water retaining wall.

Dubai Drydocks will build 120m long ship sections within the fabrication yard in the dry.

When a ship section is to be launched an enormous steel caisson gate will be closed across the basin entrance and the water level raised until the ship sections float.

Once afl at they will be manoeuvred into the basin, before the water level is lowered again. Sections will then be fl oated out and on to a drydock for assembly.

Dock floors and sills will be mass concrete. White said the design calls for an unusually robust caisson gate, measuring 65m long by 16m tall and 8m deep, and weighing 1,400t.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.