New train crew accommodation has been dropped into place by Mabey Construction at Morden underground station recently.

The two storey modular building units were fabricated by Yorkon in York. They arrived on site with glazing, internal partitioning, toilets, showers and plumbing in place.

During a 52-hour weekend possession the units were craned into position on a new 30m long bridge.

Mark Jordan, assistant project manager for London Underground says: 'The off site construction has helped us minimise the level of disruption to the operational railway.'

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.