Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Dawlish and Sidmouth sewerage improvements

Project 7

Key innovation - the partnering set up

The project has been set up on a partnering basis. The two civils designers have worked closely with one another and the civils and process contractors to share design ideas and innovations. This has meant each civils design team being involved in team meetings for the other's scheme and the sharing of design calculations and drawings between designers. Common designs are being adopted where possible and savings in time and cost are being made.

Although target costs for the two schemes were initially developed separately, one overall Agreed Target Cost has been set. Any overall savings below the ATC are to be shared by the partners up to an agreed level. Similarly, if the combined project were to overspend, the project partners would share in the additional cost.

In bringing the two schemes together and sharing the total pain/gain for the combined ATC all partners have an interest in identifying and implementing savings.

In addition to meeting capital cost targets, partners are required to meet stringent annual operating cost targets. This approach ensures that the whole life cost of the project is minimised.

Within the ATC a sum has been included for risk items. This sum has been developed by identifying all the risk items, their probabilities and the associated costs for all risks relevant to all partners.

Statistical methods have been used to set the risk sum within the ATC. This money has become part of the team budget, available to all partners where risk items occur. The payment system previously described means the project team is actively encouraged to manage all risk items, to minimise any need to draw on the risk budget. Although the risk costs are shared by the whole team, risks are managed by the partner best suited for each issue.

Lessons from the project are being used by South West Water in developing its partnering strategies.

The team

South West Water, MJ Gleeson, Paterson Candy,

Babtie Group (Dawlish), Pell Frischmann Water (Sidmouth),

Chandler KBS

Start: October 1998

Civils completion: November 1999

Operation: December 2000

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.