Cumbrian floods 'cost £276M'

Wrecked homes and businesses caused by the Cumbrian floods left a £276M bill, it was revealed today on the first anniversary of the disaster.

An estimated £124M of damage was caused to shops, farms and factories, £91M worth of damage to homes and £34M in restoring the county’s battered bridges and roads, according to figures compiled by Cumbria County Council, responsible for co-ordinating the recovery operation.

Much of the cash has been borne by the insurance industry and the taxpayer through support and grants from local and central government.

There were 25,000 flood and storm damage insurance claims according to the Association of British Insurers (ABI) with £174M paid out.

Twenty road bridges across Cumbria were destroyed or damaged but 17 of those are now open to traffic again.

The Grade II-listed Calva bridge in Workington is now expected to open early in the new year, meaning the town will once again have two working road bridges, including the temporary road bridge opened in April.

The Northside bridge, also in Workington, where PC Bill Barker was killed, is expected to be replaced by 2012.

Road damage was also spread out over a wide area with huge resurfacing and reconstruction work undertaken.

United Utilities dealt with damaged water mains and has built a new £3.4M pumping station at Willowholme in Carlisle.

And more than 2,500 tonnes of gravel and debris, strewn across farmland downstream, has still to be shifted.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.