CTRL contracts put out to tender

News

SECTION TWO of the Channel Tunnel Rail Link took a step forward last week as 12 organisations were invited by Union Railways (North) to tender for tunnelling contracts worth £600M.

The five contracts include 20km of tunnels - over half the total length of the section that will extend the CTRL from Section 1 in north Kent, under the Thames and through east London into St Pancras station.

The contracts - C220, C230, C240, C250 and C320 - are part of a total of 24 packages that make up Section 2. Many of these packages are utility and diversion contracts, some of which are already under way as part of the £277M of preparatory works.

The biggest contract not yet out to tender is Contract 310, between Ripple Lane Dagenham and Thurrock. This 7km stretch will pass over marshland on a viaduct supported on a piled slab foundation.

Union Railways (North) expects to award the contracts early next year. Each contract includes a pre-construction period of up to six months, before work on site begins in mid-2001. The entire CTRL is expected to be complete by December 2006.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.