Costain scoops £34M Manchester sewer tunnel job

Costain has won a £34M tunnelling project to tackle sewer overflows in Manchester.

The 1.8km-long tunnels are part of United Utilities’ UID (unsatisfactory intermittent discharge) scheme to clean up the Salteye Brook in Salford. UIDs occur when the sewer network overflows to a watercourse when the system is overloaded. The tunnels are designed to help prevent this by providing adequate storage capacity during heavy storms.

The tunnel route will begin at a location next to Junction 11 of the M60, passing below and then parallel to the motorway and on into the Eccles waste water treatment works.

The tunnel alignment then heads under the M60 Barton High Level Bridge parallel with the Manchester Ship Canal, past the Salford Red Devils rugby league stadium to a new outfall structure at the Port Salford Locks.

Work will begin on the project in early 2015, with the construction of deep shafts. The tunnelling will then commence in Spring 2015 with an anticipated finish a year later.

While tunnelling is underway, work will begin on a complex outfall structure adjacent to Port Salford Locks on the Manchester Ship Canal. This part of the scheme is expected to be complete in Summer 2016.

The contract also includes M&E packages.

Both tunnels are concrete lined at 2.1m and 2.85m internal diameters.

Matt Crabtree, Costain Water sector director, said: “The route crosses below the M60 motorway on and off slip roads and the main carriageway at Junction 11. It then crosses below the M60 Barton piers, narrowly avoiding raking piles from the bridge pier structures. We will continuously use the latest survey monitoring technology in real time to monitor bridge and highway structure movement before, during and after the TBM (tunnel boring machine) completes its journey.

“In order to ensure that there is minimal impacts to the sensitive Highways Agency structures, a large team of tunnel engineers will be working around the clock to ensure the project is completed successfully.”

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.