Contractor Jackson Civil Engineering last month started lifting in the first of 345 precast concrete units which will create a 320m tunnel over the Chiltern railway line at Gerrards Cross in Buckinghamshire.

Subcontractor PCE used a 160t crawler crane to lift the first 23.5t unit into place during a 29 hour railway possession.

Installation will continue at night, with about five units placed during each four hour possession. The tunnel will create 18,000m2 of land above the railway, which will be used to build a new Tesco supermarket (GE September 2003).

Designer for the work is White Young Green.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.