Contract additions

ICE news

If the project manager fails to promptly respond to 'Compensation Events' - issues raised which could lead to the project overrunning - it will be accepted as something which must be acted upon.

Key performance indicators tied in with target payments have been introduced.

Introduction of a project risk register which is created before parties tender for work and are continuously updated.

The 'early warning meeting' has been renamed the 'risk reduction meeting'.

Introduction of 'key dates' to allow smoother handover between contracts. This could be a date when electrical supply must be ready for use to allow other operations to commence.

Improving schedule of payment to contractors so they are paid as soon as work is completed, not one month or more after.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.