Construction work underway on all Olympic Village residential plots

New images released by the Olympic Delivery Authority (ODA) today show progress on the Olympic Village where building work is now underway on track on all of the residential plots.

Olympic Delivery Authority (ODA) director of property Ralph Luck said:  ‘We are continuing to make good progress on the Olympic Village site and with construction work now underway on all residential plots we are seeing the building blocks of a brand new community for east London beginning to take shape. The strong start we have made on the Olympic Village site over the past year puts us firmly on track to deliver a high quality new development for generations to come.’

The Olympic Village will comprise 11 residential plots, which are each roughly the same size as a football pitch. Each residential plot is then made up of 6 – 8 buildings built in a rectangular layout around a traditional courtyard area. Construction work started on site last summer and the huge progress on site over the past year includes:

  • Construction work now underway on all 11 residential plots
  • The first residential buildings in the Village already making their mark on the east London skyline with some buildings approaching their full height
  • Earthworks underway on the site of Chobham Academy - a world-class education campus to be built within the Olympic Village with spaces for 1,800 students aged 3 – 19
  • Over 4,000 concrete piles installed more than 20m deep to form the foundations of the Village blocks
  • Work well underway to install new electricity, gas, water, drainage and district heating services between the sites of the new housing blocks
  • Major infrastructure works including the lifting into place of two major railway bridges and new railway sidings to allow delivery of construction materials by rail to minimise congestion and pollution in east London

The Olympic Village, which lies adjacent to the Olympic Park and Stratford City sites, will accommodate athletes during the Olympic and Paralympic Games. After 2012, the Village will leave a lasting legacy for east London including:

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.