Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Christmas bonus

CONTRACTS

SIMPLEX FOUNDATIONS is installing 649 piles for the £58M phase one of the Blenheim Centre, a large redevelopment in Hounslow, Middlesex.

This phase consists of a 48,000m 2 public plaza, 334 apartments on eight floors above a 7,000m 2 supermarket, a medical centre, retail units and basement parking for 400 cars.

Simplex, working for main contractor and parent company Norwest Holst Construction under a £750,000 subcontract, arrived on site in early December. Its first task was to put in three preliminary test piles, two 600mm diameter and one 500mm diameter, designed with a safety factor of 2.

While workers tested these piles, main pile installation, designed using a factor of safety of 2.5, continued until Christmas. After satisfactory test results, the design was changed to a safety factor of 2.

The foundation contractor is using three main pile sizes for the project: 112, 750mm diameter; 352, 600mm diameter; and 185, 500mm diameter piles with depths ranging from 10-32m. All piles are being integrity tested. Six working test piles in a range of diameters and three tower crane base piles are also needed.

Simplex is installing the piles using rotary auger techniques with two Andes/5000 Watson rigs and a standby hydraulic Soilmec 312 piling rig.

It is also using an Andes service crane to install and extract casing and to install pile reinforcement cages. The temporary casing ranges from 3-9m in length.

The ground at the site has been excavated down 2m, leaving a further 3.5m of sand and gravels, with London Clay below.

Because a railway line runs past the site, Simplex has fi tted the rigs with jib arrestor ropes and slewing restraints.

Piling is due to fi nish at the end of this month.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.

Related Jobs