Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

CARDIFF COMPACTOR

PILING & FOUNDATIONS

Displacement piling is helping to avoid disturbing neighbours in Cardiff. Alexandra Wynne hears how.

When designing piles for nearly 200 homes in Cardiff, designers were asked to come up with a scheme that would minimise disruption to neighbours living as close as 6m to the site.

Traditional precast driven piles were immediately considered to be the most cost effective option but May Gurney, sub-contracted to design and install piling on the project, was forced to reconsider.

Planning restrictions meant that main contractor Bovis Homes had to take into account any noise, vibration or dust that might disturb neighbouring homes. It was down to the subcontractor to come up with a more appropriate piling design.

'It might be that noise generated by driven piling would have been at an acceptable level, but with the constant hammering sound it makes, it's more the perception of how bad it is, ' says May Gurney south west area manager, Rob Cannon.

'There were also concerns that vibrations would cause adverse effects and even structural damage to nearby homes.'

He says the company considered CFA piling as one possible solution to noise and vibration problems, but with that came a new set of issues for local residents.

The Ferry Road site, close to Cardiff Bay, is in an area where other developments have been completed with driven piling, but now there are too many homes close by. With houses near the east and south borders of the site, the company opted for displacement auger piling. Cannon believes this is the rst time displacement piling has been used in Cardiff on a job of this size.

He says while CFA would have been ef cient, it creates a large volume of spoil. The trucks needed to move this to land waste sites would have generated unwanted additional trafc around the city.

'Because you disqualify driven piling, the next logical option to consider is bored piling, ' says Cannon. 'But the amount of arisings it generates would be costly to remove from site, and logistics were a problem too.'

Displacement piling is environmentally friendlier because it cuts the amount of spoil. 'By reducing arisings you're reducing the amount of traf c coming on and off the site, which is a big plus. This was simply about saving arisings.'

Successful use of displacement piling depends on ground conditions and at Ferry Road they are good. Up to 4.5m of soft made ground sits on soft to rm clays to 13.5m and m brown silty clay with gravels to 15.5m. Dense sand, gravels and cobbles with occasional boulders and a stiff red marl appear at 19m to 20m.

The CFA auger works like a corkscrew and replaces spoil with a column of concrete. But the displacement pile boring tool is designed to shift soil laterally and downwards.

In granular soils it has the effect of compacting soils, increasing load bearing capacity, says Cannon.

The company uses a bespoke boring tool. 'The pitch and angulation of the ights are designed to push material to the sides and down, ' says Cannon. Once the tool reaches depth, it works in a similar way to CFA, lling the void with pumped concrete through the hollow stem as the auger is retracted.

Displacement piling does generate some spoil as the auger emerges at the surface, but much less than with CFA, says Cannon.

'If driven piles are ruled out, we'll always go for displacement instead of replacement. If you take the ground out, you have to nd a way to get rid of it.'

The company is using two of its largest rigs, a 49t Woltman THW 4019-D and a 78t Llamada P-150TT, to install 634 piles at 15m to 19m depths depending on where stronger ground appears. Company foreman at Ferry Road, Steven Anderson, explains the Woltman has the added bene t of being able to turn 360º. This factor is helping to complete one pile about every 15 minutes.

Preliminary pile load tests done in mid-December proved the piling design down to a maximum depth of 19m and to a safety factor of 2.5 times 550kN - the maximum load required for any pile.

Cannon sees a lot of potential for this method. 'Because there is now so much pressure on contractors to consider environmental issues, displacement piling will look like a more attractive option and could become the next big thing.'

The 350mm diameter piles are strengthened by 6m long steel reinforcement bars with two collars. All of the piling was due to be completed as GE went to press.

Ground works contractor WD Lewis is sub-contracted to pick up where May Gurney leaves off. It has responsibility for completing ring beams before work on external structures can begin.

The development of one and two bedroom apartments and houses is expected to complete by mid-2009.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.