Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to a newer version or another browser.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Crossrail boss ‘cautiously confident’ on opening

06 cable management systems installed in crossrail tunnel 3x2

Crossrail chief executive officer Andrew Wolstenholme has said he is “cautiously confident” the line will open on time.

Speaking at the Westminster Forum event ’Delivering Crossrail and next steps for Crossrail 2’, he said there were five items still on the critical path to allow the line to open on time: completion of the stations, £2.3bn worth of work which Network Rail must complete on the Great Western Main Line and Anglian Rail, introduction of the rolling stock and depots, and the property above the stations.

Wolstenholme described the Network Rail aspect of the remaining work as a “hugely complicated programme of work” but he was confident the organisation was “very well planned and organised” and could finish the work on time.

“Some of things are highly visible [Network Rail has to do] and demonstrable as to whether they’ve done it or not,” he said. Some of the work they’ve done over Christmas applying the data overlay to the very complicated signalling systems are some of the things you can’t see. But Network Rail are very, very well planned and organised to do that work.”

He said in the past, issues had arisen for Network Rail but since then it had improved significantly.

“Three or four years ago, there were some overruns and those were very public,” he said. “But for the last two Christmases you haven’t been able to write about them because Network Rail has done it so well.

“We’re confident that Network Rail can do the work on time, but you have to manage these risks carefully so you can’t be sure, but we’re cautiously confident about that.”

On stations Wolstenholme said station finishes were going in on some stations and others would need a further six to seven months to complete.

Readers' comments (2)

  • Thanks Katherine. An interesting article about whether or not Crossrail will open on time, but no mention of when on the scheduled opening date actually is??!

    Unsuitable or offensive? Report this comment

  • Jason Le Masurier

    Proof reader ?!!

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.

Related Jobs