BP rushed rig work – presidential inquiry

Oil giant BP too often operated in a rush during the closing days of work on its doomed Gulf of Mexico well, a US presidential inquiry has said.

The company was accused of being hurried and making confusing, last-minute changes to plans that were unusual in the complex environment of deep water.

The White House oil spill commission said BP could have operated more safely if the company took the time to get the necessary equipment and materials.

“We are aware of what appeared to be a rush to completion,” commission co-chairman William Reilly said. What is unclear, he said, is what drove people to determine they could not wait for equipment and materials to perform operations more safely.

Lawyers investigating the 20 April disaster have said they found no evidence that anyone aboard the rig or on shore made a conscious decision to sacrifice safety for money.

But the panel’s leaders made clear today that the findings overall exposed a lack of safety culture on the rig, with Reilly blasting all three companies involved – BP, Halliburton, and Transocean – as “laggards” in the industry and in “need of top-to-bottom reform.”

Much of the scrutiny focused on the company’s plan to temporarily plug the well, which investigators with the presidential commission said added to the risk of a blowout. Plugging the well is a procedure used to seal it off until the company comes back to produce oil and gas.

Experts questioned BP’s use of a single plug in the process. Charlie Williams, a chief scientist with Shell Energy Resources, said the company used a minimum of three plugs in its deepwater wells.

BP also chose to fill the well with seawater, rather than heavy drilling mud, leaving it vulnerable to an upsurge of oil and gas – a condition that is not allowed for exploratory wells drilled in other places, experts said.

The company also chose not to use mechanical plugs, devices put inside the pipe that also can block oil and gas.

Many of the decisions would have required additional time and materials, said Steve Lewis, an advanced drilling technology engineer with Seldovia Marine Services who reviewed BP’s drilling plans, federal permits and communications on behalf of the commission.

“I know there was pressure on these people to get done and move on,” Lewis said. “The apparent shuffling and scrambling was not really necessary.”


Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.