A TOUGH CALL

PILING - Contractors rise to the awesome challenge of installing piles for port facilities in New Caledonia's technically tough and environmentally sensitive Bay of Prony.

Contractor Seacore is tackling one of the world's most technically and environmentally challenging foundation drilling projects in the Bay of Prony, at the southern end of New Caledonia.

The company is installing piles for two berthing wharves with approach jetties, part of the new port facilities for the massive $1.88bn (£989M) Goro Nickel Development Project.

Work involves piling and specialist foundation drilling techniques to install tubular steel piles in the foreshore through highly variable ground. It is randomly peppered with exceptionally large and hard igneous Gabbro rocks, with a compressive strength up to 250MPa.

Raking and vertical compression piles are 914mm diameter, ranging from 16m to 48m long. The 102 vertical bearing piles are installed individually in rows. The 24 rocksocketed rakers are in clusters.

All have to accommodate an ultimate compressive load of 1,130t and tension load of 835t. The piles are interlinked with precast concrete crosshead beams, which are spanned with precast concrete deck panels and overlaid with a nal cast in situ concrete deck slab.

The port and nickel mine are expected to be operational by late summer. 'The drilling conditions have been very challenging, ' says Seacore specialist marine services divisional manager Jason Clark.

'Piles have had to be installed through sand, clays and Gabbro Saprolite, which is a friable and decomposed Gabbro, also known as rotten granite. This is randomly intermingled with extremely hard Gabbro core rocks, some the size of a pickup truck.

'Stringent environmental protection measures have to be adhered to. These have involved the use of marine silt screens during drilling operations to prevent suffocation of the coral reefs in the surrounding lagoon - the area's a breeding and calving ground for Humpback Whales, ' says Clark.

To install the piles, Seacore is using a vibratory pile driver and a 20t hydraulic drop hammer, combined with a reverse circulation under-reaming hammer and its own reverse circulation drill rig. All the equipment is operated from a Dutch jack up barge supplied to the main civil works contractor, a joint venture of McConnell Dowell Constructors, Vinci Grands Projects and local New Caledonia contractors Socalmo and Dumez DTH. Civils work is worth £35M.

After assessing ground conditions, Seacore selected a down-thehole hammer as the best solution to tackle the very hard Gabbro, as the penetration rates would be significantly greater than conventional reverse circulation drilling.

But Seacore also considered a reverse circulation system was essential in this environmentally sensitive area. Conventional ushing systems would typically discharge into the sea.

Installation involved driving the piles to refusal with the vibrating hammer, then using the drop hammer to take them further and toe them into bedrock. Drilling was then used to create 4.5m deep rock sockets.

Seacore moved onto site in late autumn 2005 and started on the rst hole last January.

Initially the toes of the thin walled steel tubes buckled and deformed when hitting the Gabbro core stones or bedrock and the site team had to adapt their piling operations to the extreme ground conditions.

This involved welding a heattreated shoe with a strength of 1,500MPa onto the bottom of the piles. This resolved the deformation problem.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Please note comments made online may also be published in the print edition of New Civil Engineer. Links may be included in your comments but HTML is not permitted.